| Action Date | Action Description | 
|---|---|
| Jan 04, 2007 | Assent Application Received | 
| Jan 05, 2007 | Administrative Review for Completeness | 
| Jan 10, 2007 | Team Review for Completeness | 
| Jan 10, 2007 | Team Review for Completeness | 
| Jan 10, 2007 | Application Accepted | 
| Feb 06, 2007 | HPHC Historical Preservation No Effect | 
| Apr 21, 2008 | Additional Information Received | 
| Feb 02, 2009 | Plans Received | 
| Feb 13, 2009 | Plans Received | 
| Feb 16, 2009 | Typist for Processing | 
| Feb 16, 2009 | Executive Sign Off | 
| Feb 16, 2009 | Sent to Photo Copy | 
| Feb 16, 2009 | Permit Approved | 
| Feb 16, 2009 | Biologist Report | 
| Feb 16, 2009 | Engineering Report | 
| Feb 20, 2009 | Land Evidence Date | 
| Jun 23, 2009 | Commencement of Work Notice received |