| Action Date | Action Description | 
|---|---|
| Legal Response/Decision | |
| Feb 05, 2007 | Assent Application Received | 
| Feb 09, 2007 | Administrative Review for Completeness | 
| Feb 12, 2007 | Team Review for Completeness | 
| Feb 12, 2007 | Team Review for Completeness | 
| Feb 12, 2007 | Application Accepted | 
| Feb 12, 2007 | Category B assigned | 
| Feb 20, 2007 | HPHC Historical Preservation No Effect | 
| Mar 02, 2007 | 30 day Public Notice Issued | 
| Mar 15, 2007 | Correspondence Mailed/Faxed/E-mailed | 
| Apr 02, 2007 | Public Notice End Date | 
| Apr 03, 2007 | Correspondence Received | 
| Apr 23, 2007 | US Army Corp of Engineers Permit Date | 
| Apr 25, 2007 | US Army Corps of Engineers Approval Received | 
| May 10, 2007 | Executive Sign Off | 
| May 10, 2007 | Biologist Report | 
| May 10, 2007 | Engineering Report | 
| Jun 12, 2007 | Ready to Schedule Semi-Monthly Meeting | 
| Jun 18, 2007 | Mail Agenda Notice | 
| Jul 02, 2007 | Council Approval Granted | 
| Jul 02, 2007 | Semi-Monthly Meeting Held | 
| Jul 02, 2007 | Continued Application by the Council | 
| Aug 14, 2007 | Stipulation Package from Biologist | 
| Aug 14, 2007 | Stipulation Package by Engineer | 
| Aug 14, 2007 | Permit Approved | 
| Aug 14, 2007 | Under Review/Decision | 
| Oct 17, 2007 | Land Evidence Date |