| Action Date | Action Description | 
|---|---|
| Feb 13, 2007 | Assent Application Received | 
| Feb 14, 2007 | Administrative Review for Completeness | 
| Feb 15, 2007 | Deficient Application - Owner Notification Sent | 
| Feb 19, 2007 | Deficient Application Picked Up | 
| Apr 30, 2007 | Deficiency Response Received | 
| May 15, 2007 | Administrative Review for Completeness | 
| May 15, 2007 | Team Review for Completeness | 
| May 15, 2007 | Team Review for Completeness | 
| May 15, 2007 | Application Accepted | 
| May 16, 2007 | Additional Information Requested from Applicant | 
| May 22, 2007 | 30 day Public Notice Issued | 
| May 29, 2007 | Biologist Report | 
| May 29, 2007 | Engineering Report | 
| Jun 05, 2007 | Public Notice End Date Extension Granted | 
| Jun 05, 2007 | 30 day Public Notice Issued | 
| Jun 06, 2007 | Public Notice End Date | 
| Jun 12, 2007 | Correspondence Received | 
| Jun 13, 2007 | Public Notice End Date | 
| Jun 14, 2007 | Executive Sign Off | 
| Jun 14, 2007 | Sent to Photo Copy | 
| Jun 14, 2007 | Typist for Processing | 
| Jun 14, 2007 | Permit Approved | 
| Jun 25, 2007 | HPHC Historical Preservation No Effect | 
| Jul 13, 2007 | Land Evidence Date | 
| Jul 30, 2007 | Correspondence Received | 
| Feb 22, 2008 | Correspondence Received | 
| Apr 12, 2012 | Modification Request | 
| Apr 16, 2012 | Administrative Review for Completeness | 
| Apr 17, 2012 | Team Review for Completeness | 
| Apr 17, 2012 | Team Review for Completeness | 
| Apr 25, 2012 | Additional Information Received | 
| May 02, 2012 | Additional Information Received | 
| May 04, 2012 | Biologist Report | 
| May 07, 2012 | Typist for Processing | 
| May 07, 2012 | Executive Sign Off | 
| May 07, 2012 | Sent to Photo Copy | 
| May 07, 2012 | Modification Approved | 
| May 15, 2012 | Land Evidence Date | 
| Jun 01, 2012 | Land Evidence Date | 
| Oct 15, 2013 | Consent Agreement signed/received | 
| Oct 25, 2013 | Additional Information Received |