| Action Date | Action Description | 
|---|---|
| Jun 29, 2007 | Assent Application Received | 
| Jul 02, 2007 | Administrative Review for Completeness | 
| Jul 13, 2007 | Team Review for Completeness | 
| Jul 13, 2007 | Team Review for Completeness | 
| Jul 13, 2007 | Deficient Application - Owner Notification Sent | 
| Sep 27, 2007 | Deficient Application Discarded/No deficiency Reponse | 
| Nov 08, 2007 | Deficiency Response Received | 
| Nov 09, 2007 | Administrative Review for Completeness | 
| Nov 15, 2007 | Team Review for Completeness | 
| Nov 15, 2007 | Team Review for Completeness | 
| Nov 15, 2007 | Application Accepted | 
| Nov 15, 2007 | Category A* (Docks) | 
| Nov 20, 2007 | Plans Received | 
| Nov 24, 2007 | HPHC Historical Preservation No Effect | 
| Jan 16, 2008 | 30 day Public Notice Issued | 
| Feb 16, 2008 | Public Notice End Date | 
| Mar 14, 2008 | Dock Meeting -- Approval | 
| Mar 24, 2008 | Plans Received | 
| Apr 08, 2008 | Biologist Report | 
| Apr 08, 2008 | Engineering Report | 
| Apr 09, 2008 | Typist for Processing | 
| Apr 09, 2008 | Executive Sign Off | 
| Apr 09, 2008 | Sent to Photo Copy | 
| Apr 09, 2008 | Permit Approved | 
| Apr 21, 2008 | Land Evidence Date | 
| May 05, 2008 | US Army Corp of Engineers Permit Date | 
| May 08, 2008 | US Army Corps of Engineers Approval Received |