| Action Date | Action Description | 
|---|---|
| Aug 03, 2007 | Assent Application Received | 
| Aug 03, 2007 | Administrative Review for Completeness | 
| Aug 08, 2007 | Team Review for Completeness | 
| Aug 08, 2007 | Team Review for Completeness | 
| Aug 08, 2007 | Application Accepted | 
| Aug 08, 2007 | Deficiency - Phone Call to Applicant/Owner | 
| Aug 08, 2007 | Category A* (Docks) | 
| Aug 16, 2007 | Additional Information Received | 
| Aug 20, 2007 | HPHC Historical Preservation No Effect | 
| Sep 21, 2007 | 30 day Public Notice Issued | 
| Oct 21, 2007 | Public Notice End Date | 
| Jan 16, 2008 | Dock Meeting Scheduled (Admin) | 
| Jan 29, 2008 | Biologist Report | 
| Jan 29, 2008 | Engineering Report | 
| Jan 30, 2008 | Typist for Processing | 
| Jan 30, 2008 | Executive Sign Off | 
| Jan 30, 2008 | Sent to Photo Copy | 
| Jan 30, 2008 | Permit Approved | 
| Feb 06, 2008 | US Army Corps of Engineers Approval Received | 
| Mar 28, 2008 | Land Evidence Date |