| Action Date | Action Description | 
|---|---|
| Sep 12, 2007 | Assent Application Received | 
| Sep 13, 2007 | Administrative Review for Completeness | 
| Sep 17, 2007 | Team Review for Completeness | 
| Sep 17, 2007 | Team Review for Completeness | 
| Sep 17, 2007 | Deficient Application - Owner Notification Sent | 
| Sep 21, 2007 | Deficiency Response Received | 
| Sep 25, 2007 | Plans Received | 
| Oct 01, 2007 | Team Review for Completeness | 
| Oct 01, 2007 | Team Review for Completeness | 
| Oct 01, 2007 | Application Accepted | 
| Oct 09, 2007 | Biologist Report | 
| Oct 09, 2007 | Engineering Report | 
| Oct 09, 2007 | Typist for Processing | 
| Oct 09, 2007 | Executive Sign Off | 
| Oct 09, 2007 | Sent to Photo Copy | 
| Oct 09, 2007 | Permit Approved | 
| Nov 01, 2007 | Land Evidence Date |