| Action Date | Action Description | 
|---|---|
| Sep 28, 2007 | Maintenance Certification Request | 
| Oct 01, 2007 | Administrative Review for Completeness | 
| Oct 02, 2007 | Team Review for Completeness | 
| Oct 02, 2007 | Team Review for Completeness | 
| Oct 02, 2007 | Application Accepted | 
| Oct 17, 2007 | Biologist Report | 
| Oct 17, 2007 | Engineering Report | 
| Oct 17, 2007 | Typist for Processing | 
| Oct 17, 2007 | Executive Sign Off | 
| Oct 17, 2007 | Sent to Photo Copy | 
| Oct 17, 2007 | Permit Approved | 
| Oct 26, 2007 | HPHC Historical Preservation No Effect | 
| Oct 31, 2007 | Land Evidence Date | 
| Mar 18, 2008 | Modification Request | 
| Mar 31, 2008 | Biologist Report | 
| Mar 31, 2008 | Engineering Report | 
| Apr 01, 2008 | Typist for Processing | 
| Apr 01, 2008 | Executive Sign Off | 
| Apr 01, 2008 | Sent to Photo Copy | 
| Apr 01, 2008 | Modification Approved | 
| Apr 09, 2008 | HPHC Historical Preservation No Effect |