| Action Date | Action Description | 
|---|---|
| Nov 14, 2007 | Assent Application Received | 
| Nov 16, 2007 | Administrative Review for Completeness | 
| Nov 19, 2007 | Team Review for Completeness | 
| Nov 19, 2007 | Team Review for Completeness | 
| Nov 19, 2007 | Application Accepted | 
| Nov 19, 2007 | Category B assigned | 
| Dec 03, 2007 | 30 day Public Notice Issued | 
| Dec 03, 2007 | Additional Information Received | 
| Dec 09, 2007 | Public Notice End Date Extension Granted | 
| Jan 02, 2008 | HPHC Historical Preservation No Effect | 
| Jan 03, 2008 | Public Notice End Date | 
| Jan 29, 2008 | Correspondence Received | 
| Feb 22, 2008 | Engineering Report | 
| Feb 29, 2008 | Executive Signoff of Staff Reports | 
| Feb 29, 2008 | Biologist Report | 
| May 05, 2008 | Ready to Schedule Semi-Monthly Meeting | 
| May 05, 2008 | Mail Agenda Notice | 
| May 13, 2008 | Semi-Monthly Meeting Postponed | 
| May 13, 2008 | Semi-Monthly Meeting Date Scheduled | 
| Jun 04, 2008 | US Army Corp of Engineers Permit Date | 
| Jun 04, 2008 | US Army Corp of Engineers Permit Date | 
| Jun 06, 2008 | US Army Corps of Engineers Approval Received | 
| Jun 06, 2008 | US Army Corps of Engineers Approval Received | 
| Jun 11, 2008 | Ready to Schedule Semi-Monthly Meeting | 
| Jun 11, 2008 | Mail Agenda Notice | 
| Jun 24, 2008 | Semi-Monthly Meeting Held | 
| Jun 24, 2008 | Council Approval Granted | 
| Jun 24, 2008 | Semi-Monthly Meeting Date Scheduled | 
| Jul 31, 2008 | Typist for Processing | 
| Jul 31, 2008 | Executive Sign Off | 
| Jul 31, 2008 | Sent to Photo Copy | 
| Jul 31, 2008 | Permit Approved | 
| Aug 07, 2008 | Commencement of Work Notice received | 
| Aug 11, 2008 | Legal Response/Decision | 
| Aug 13, 2008 | Land Evidence Date |