| Action Date | Action Description | 
|---|---|
| Dec 28, 2007 | Assent Application Received | 
| Jan 07, 2008 | Administrative Review for Completeness | 
| Jan 31, 2008 | Team Review for Completeness | 
| Feb 01, 2008 | Deficient Application - Owner Notification Sent | 
| Feb 28, 2008 | Deficiency Response Received | 
| Mar 11, 2008 | Plans Received | 
| Mar 17, 2008 | Application Accepted | 
| Mar 31, 2008 | Plans Received | 
| Apr 30, 2008 | 30 day Public Notice Issued | 
| May 15, 2008 | Objections/Comments Received | 
| May 21, 2008 | Objections/Comments Received | 
| Nov 03, 2008 | US Army Corp of Engineers Permit Date | 
| Nov 05, 2008 | US Army Corps of Engineers Approval Received | 
| Dec 19, 2008 | Correspondence Mailed/Faxed/E-mailed | 
| Mar 16, 2009 | Biologist Report | 
| Mar 16, 2009 | Engineering Report | 
| Mar 18, 2009 | Supervisor Biologist SignOff | 
| Mar 23, 2009 | Supervisor Engineer SignOff | 
| Mar 23, 2009 | Executive Signoff of Staff Reports | 
| Apr 13, 2009 | Ready to Schedule Semi-Monthly Meeting | 
| Apr 13, 2009 | Mail Agenda Notice | 
| Apr 28, 2009 | Semi-Monthly Meeting Held | 
| Apr 28, 2009 | Council Decision - Denied | 
| Apr 28, 2009 | Semi-Monthly Meeting Date Scheduled | 
| Mar 15, 2011 | Application Cancelled |