| Action Date | Action Description | 
|---|---|
| May 08, 2009 | Assent Application Received | 
| May 11, 2009 | Administrative Review for Completeness | 
| May 27, 2009 | Deficient Application Picked Up | 
| Jul 13, 2009 | Deficiency Response Received | 
| Jul 14, 2009 | Team Review for Completeness | 
| Jul 14, 2009 | Team Review for Completeness | 
| Jul 14, 2009 | Application Accepted | 
| Aug 18, 2009 | Correspondence Mailed/Faxed/E-mailed | 
| Aug 27, 2009 | HPHC Historical Preservation No Effect | 
| Sep 04, 2009 | Plans Received | 
| Sep 25, 2009 | Biologist Report | 
| Sep 28, 2009 | Engineering Report | 
| Sep 30, 2009 | Typist for Processing | 
| Sep 30, 2009 | Executive Sign Off | 
| Sep 30, 2009 | Permit Approved | 
| Oct 01, 2009 | Sent to Photo Copy | 
| Oct 22, 2009 | Land Evidence Date | 
| Jul 19, 2012 | Extension Toll letter mailed | 
| Feb 21, 2014 | Additional Information Received | 
| Oct 24, 2014 | Modification Request | 
| Nov 25, 2014 | Modification Request | 
| Dec 09, 2014 | Biologist Report | 
| Dec 10, 2014 | Correspondence Received | 
| Dec 11, 2014 | Typist for Processing | 
| Dec 11, 2014 | Modification Approved | 
| Dec 12, 2014 | Executive Sign Off | 
| Dec 12, 2014 | Sent to Photo Copy | 
| Jan 06, 2015 | Land Evidence Date | 
| Jan 20, 2015 | HPHC Historical Preservation No Effect | 
| Jun 12, 2015 | 30 Day Appeal Notification to Owner |