| Action Date | Action Description | 
|---|---|
| Mar 15, 2010 | Assent Application Received | 
| Mar 16, 2010 | Administrative Review for Completeness | 
| Mar 25, 2010 | Team Review for Completeness | 
| Mar 25, 2010 | Deficient Application - Owner Notification Sent | 
| Nov 18, 2010 | Deficiency Response Received | 
| Nov 22, 2010 | Team Review for Completeness | 
| Nov 22, 2010 | Application Accepted | 
| Nov 22, 2010 | Category B assigned | 
| Nov 30, 2010 | 30 day Public Notice Issued | 
| Dec 02, 2010 | HPHC Historical Preservation No Effect | 
| Dec 30, 2010 | Public Notice End Date | 
| Jan 10, 2011 | Correspondence Received | 
| Mar 28, 2011 | Additional Information Received | 
| Mar 29, 2011 | Typist for Processing | 
| Mar 29, 2011 | Biologist Report | 
| Mar 29, 2011 | Engineering Report | 
| Mar 29, 2011 | Permit Approved | 
| Mar 31, 2011 | Executive Sign Off | 
| Mar 31, 2011 | Sent to Photo Copy | 
| Apr 20, 2011 | Land Evidence Date |