| Action Date | Action Description | 
|---|---|
| Sep 13, 2010 | Assent Application Received | 
| Sep 13, 2010 | Administrative Review for Completeness | 
| Sep 14, 2010 | Team Review for Completeness | 
| Sep 14, 2010 | Team Review for Completeness | 
| Sep 14, 2010 | Application Accepted | 
| Sep 30, 2010 | Additional Information Received | 
| Oct 06, 2010 | Additional Information Received | 
| Oct 07, 2010 | 30 day Public Notice Issued | 
| Oct 25, 2010 | US Army Corp of Engineers Permit Date | 
| Nov 07, 2010 | Public Notice End Date | 
| Nov 15, 2010 | Dock Meeting -- Approval | 
| Nov 16, 2010 | HPHC Historical Preservation No Effect | 
| Nov 16, 2010 | Biologist Report | 
| Nov 16, 2010 | Engineering Report | 
| Nov 17, 2010 | Permit Approved | 
| Nov 17, 2010 | Category A* (Docks) | 
| Nov 17, 2010 | Typist for Processing | 
| Nov 19, 2010 | Executive Sign Off | 
| Nov 19, 2010 | Sent to Photo Copy | 
| Nov 24, 2010 | Land Evidence Date | 
| Dec 22, 2010 | Commencement of Work Notice received |