| Action Date | Action Description | 
|---|---|
| Sep 30, 2010 | Assent Application Received | 
| Oct 01, 2010 | Administrative Review for Completeness | 
| Oct 28, 2010 | Team Review for Completeness | 
| Oct 28, 2010 | Application Accepted | 
| Nov 15, 2010 | Engineering Report | 
| Nov 17, 2010 | Typist for Processing | 
| Nov 17, 2010 | Permit Approved | 
| Nov 18, 2010 | Executive Sign Off | 
| Nov 18, 2010 | Sent to Photo Copy | 
| Nov 22, 2010 | HPHC Historical Preservation No Effect |