| Action Date | Action Description | 
|---|---|
| Nov 04, 2010 | Assent Application Received | 
| Nov 05, 2010 | Administrative Review for Completeness | 
| Nov 17, 2010 | Additional Information Received | 
| Nov 19, 2010 | Deficient Application Picked Up | 
| Nov 19, 2010 | Team Review for Completeness | 
| Dec 08, 2010 | Deficiency Response Received | 
| Dec 29, 2010 | Team Review for Completeness | 
| Jan 26, 2011 | 30 day Public Notice Issued | 
| Feb 25, 2011 | Public Notice End Date | 
| May 10, 2011 | Engineering Report | 
| Jun 14, 2011 | US Army Corps of Engineers Approval Received | 
| Jun 16, 2011 | Permit Approved | 
| Jun 16, 2011 | Typist for Processing | 
| Jun 16, 2011 | Executive Sign Off | 
| Jun 16, 2011 | Sent to Photo Copy | 
| Jun 24, 2011 | Land Evidence Date | 
| Jul 01, 2011 | Commencement of Work Notice received |