| Action Date | Action Description | 
|---|---|
| Nov 23, 2010 | Assent Application Received | 
| Nov 26, 2010 | Administrative Review for Completeness | 
| Nov 30, 2010 | Team Review for Completeness | 
| Nov 30, 2010 | Application Accepted | 
| Dec 06, 2010 | 30 day Public Notice Issued | 
| Dec 08, 2010 | HPHC Historical Preservation No Effect | 
| Jan 06, 2011 | Public Notice End Date | 
| Jan 13, 2011 | Objections/Comments Received | 
| Apr 08, 2011 | Objections/Comments Received | 
| Nov 23, 2012 | Additional Information Received | 
| Dec 13, 2012 | 30 day Public Notice Issued | 
| Jan 13, 2013 | Public Notice End Date | 
| Jan 14, 2013 | Dock/1.1.6 Review approval | 
| Jan 15, 2013 | Biologist Report | 
| Feb 04, 2013 | Permit Approved | 
| Feb 04, 2013 | Typist for Processing | 
| Feb 04, 2013 | Category A* (Docks) | 
| Feb 05, 2013 | Executive Sign Off | 
| Feb 05, 2013 | Sent to Photo Copy | 
| Feb 20, 2013 | US Army Corp of Engineers Permit Date | 
| Jun 24, 2015 | Land Evidence Date | 
| Sep 14, 2018 | Expiration of Assent/End of Tolling Legislation | 
| Oct 10, 2018 | Extension of Permit Request | 
| Nov 26, 2018 | Enforcement Compliance Inspection Required | 
| Nov 26, 2018 | Process Extension | 
| Nov 26, 2018 | Extension Approved |