| Action Date | Action Description | 
|---|---|
| Dec 29, 2010 | Assent Application Received | 
| Dec 29, 2010 | Administrative Review for Completeness | 
| Dec 29, 2010 | Team Review for Completeness | 
| Jan 21, 2011 | Deficient Application - Owner Notification Sent | 
| Feb 04, 2011 | Deficient Application Picked Up | 
| Apr 05, 2011 | Deficiency Response Received | 
| Apr 11, 2011 | Team Review for Completeness | 
| Apr 11, 2011 | Application Accepted | 
| Apr 19, 2011 | HPHC Historical Preservation No Effect | 
| Jun 07, 2011 | Biologist Report | 
| Jun 13, 2011 | Typist for Processing | 
| Jun 13, 2011 | Executive Sign Off | 
| Jun 13, 2011 | Sent to Photo Copy | 
| Jun 13, 2011 | Permit Approved | 
| Nov 16, 2011 | Land Evidence Date | 
| Jun 27, 2014 | Commencement of Work Notice received | 
| Jan 14, 2015 | Correspondence Received |