| Action Date | Action Description | 
|---|---|
| Apr 04, 2011 | Assent Application Received | 
| Apr 05, 2011 | Administrative Review for Completeness | 
| Apr 14, 2011 | Team Review for Completeness | 
| Apr 14, 2011 | Team Review for Completeness | 
| Apr 14, 2011 | Application Accepted | 
| Apr 26, 2011 | HPHC Historical Preservation No Effect | 
| May 17, 2011 | 30 day Public Notice Issued | 
| Jun 17, 2011 | Public Notice End Date | 
| Aug 24, 2011 | Additional Information Received | 
| Nov 08, 2011 | Additional Information Received | 
| Nov 23, 2011 | Biologist Report | 
| Nov 29, 2011 | Engineering Report | 
| Dec 05, 2011 | Category A* (Docks) | 
| Dec 06, 2011 | Typist for Processing | 
| Dec 06, 2011 | Permit Approved | 
| Dec 08, 2011 | Executive Sign Off | 
| Dec 08, 2011 | Sent to Photo Copy | 
| Dec 22, 2011 | US Army Corps of Engineers Approval Received | 
| Jan 05, 2012 | Land Evidence Date |