| Action Date | Action Description | 
|---|---|
| Oct 25, 2011 | Assent Application Received | 
| Oct 26, 2011 | Administrative Review for Completeness | 
| Nov 01, 2011 | Team Review for Completeness | 
| Nov 01, 2011 | Team Review for Completeness | 
| Nov 01, 2011 | Category B assigned | 
| Nov 01, 2011 | Application Accepted | 
| Nov 14, 2011 | 30 day Public Notice Issued | 
| Nov 23, 2011 | HPHC Historical Preservation No Effect | 
| Dec 01, 2011 | Public Notice End Date Extension Granted | 
| Dec 14, 2011 | Objections/Comments Received | 
| Dec 14, 2011 | Public Notice End Date | 
| Dec 27, 2011 | Biologist Report | 
| Dec 27, 2011 | Engineering Report | 
| Jan 10, 2012 | Semi-Monthly Meeting Held | 
| Jan 10, 2012 | Council Approval Granted | 
| Jan 13, 2012 | Correspondence Received | 
| Jan 19, 2012 | US Army Corps of Engineers Approval Received | 
| Jan 20, 2012 | Plans Received | 
| Jan 25, 2012 | Permit Approved | 
| Jan 25, 2012 | Stipulation Package from Biologist | 
| Jan 25, 2012 | Stipulation Package by Engineer | 
| Jan 25, 2012 | Legal Response/Decision | 
| Jan 27, 2012 | Typist for Processing | 
| Jan 30, 2012 | Executive Sign Off | 
| Jan 30, 2012 | Sent to Photo Copy | 
| Feb 07, 2012 | Land Evidence Date |