| Action Date | Action Description | 
|---|---|
| May 21, 2012 | Assent Application Received | 
| May 22, 2012 | Administrative Review for Completeness | 
| May 22, 2012 | Team Review for Completeness | 
| May 22, 2012 | Team Review for Completeness | 
| May 22, 2012 | Application Accepted | 
| Jun 14, 2012 | Additional Information Received | 
| Jun 19, 2012 | Correspondence Mailed/Faxed/E-mailed | 
| Jun 04, 2013 | Additional Information Received | 
| Jun 04, 2013 | Biologist Report | 
| Jun 04, 2013 | Engineering Report | 
| Jun 06, 2013 | Typist for Processing | 
| Jun 06, 2013 | Executive Sign Off | 
| Jun 06, 2013 | Sent to Photo Copy | 
| Jun 06, 2013 | Permit Approved | 
| Jun 13, 2013 | Land Evidence Date |