| Action Date | Action Description | 
|---|---|
| Executive Sign Off | |
| Aug 17, 2012 | Assent Application Received | 
| Aug 17, 2012 | Administrative Review for Completeness | 
| Aug 23, 2012 | Team Review for Completeness | 
| Aug 23, 2012 | Team Review for Completeness | 
| Aug 23, 2012 | Application Accepted | 
| Sep 01, 2012 | HPHC Historical Preservation No Effect | 
| Oct 23, 2012 | Plans Received | 
| Nov 29, 2012 | 30 day Public Notice Issued | 
| Jan 11, 2013 | US Army Corps of Engineers Approval Received | 
| Jan 14, 2013 | Mail Agenda Notice | 
| Jan 22, 2013 | Continued Application by the Council | 
| Jan 22, 2013 | Semi-Monthly Meeting Date Scheduled | 
| Jan 29, 2013 | Mail Agenda Notice | 
| Feb 12, 2013 | Semi-Monthly Meeting Date Scheduled | 
| Feb 12, 2013 | Semi-Monthly Meeting Held | 
| Feb 12, 2013 | Council Approval Granted | 
| Feb 13, 2013 | Engineering Report | 
| Feb 13, 2013 | Biologist Report | 
| Feb 14, 2013 | Typist for Processing | 
| Feb 18, 2013 | Sent to Photo Copy | 
| Feb 18, 2013 | Permit Approved | 
| Feb 19, 2013 | Legal Response/Decision |