| Action Date | Action Description | 
|---|---|
| Mar 28, 2013 | Assent Application Received | 
| Mar 29, 2013 | Administrative Review for Completeness | 
| Apr 02, 2013 | Team Review for Completeness | 
| Apr 02, 2013 | Team Review for Completeness | 
| Apr 02, 2013 | Application Accepted | 
| Apr 02, 2013 | Category B assigned | 
| Apr 10, 2013 | 30 day Public Notice Issued | 
| Apr 16, 2013 | Public Hearing Notices Mailed | 
| May 06, 2013 | HPHC Historical Preservation No Effect | 
| May 10, 2013 | Correspondence Received | 
| May 10, 2013 | Public Notice End Date | 
| May 20, 2013 | Biologist Report | 
| May 20, 2013 | Engineering Report | 
| May 28, 2013 | Semi-Monthly Meeting Date Scheduled | 
| May 28, 2013 | Water Quality Certification | 
| May 28, 2013 | Council Approval Granted | 
| May 28, 2013 | Semi-Monthly Meeting Held | 
| Jun 10, 2013 | Stipulation Package by Engineer | 
| Jun 25, 2013 | Legal Response/Decision | 
| Jun 25, 2013 | Under Review/Decision | 
| Jun 25, 2013 | 30 Day Appeal Notification to Owner | 
| Jun 26, 2013 | Stipulation Package from Biologist | 
| Jul 17, 2013 | Typist for Processing | 
| Jul 17, 2013 | Executive Sign Off | 
| Jul 17, 2013 | Sent to Photo Copy | 
| Jul 17, 2013 | Permit Approved | 
| Aug 01, 2013 | Modification Request | 
| Aug 06, 2013 | Engineering Report | 
| Aug 06, 2013 | Biologist Report | 
| Aug 06, 2013 | Engineering Report | 
| Aug 07, 2013 | Typist for Processing | 
| Aug 07, 2013 | Modification Approved | 
| Aug 08, 2013 | Executive Sign Off | 
| Aug 08, 2013 | Sent to Photo Copy | 
| Aug 19, 2013 | Water Quality Certification | 
| Oct 07, 2013 | US Army Corps of Engineers Approval Received |