| Action Date | Action Description | 
|---|---|
| Oct 20, 2003 | Additional Information Received | 
| Mar 04, 2014 | Administrative Review for Completeness | 
| Apr 03, 2014 | Team Review for Completeness | 
| Apr 03, 2014 | File Closed | 
| May 19, 2014 | Deficiency Response Received | 
| May 21, 2014 | Team Review for Completeness | 
| May 21, 2014 | Application Accepted | 
| May 27, 2014 | HPHC Historical Preservation No Effect | 
| Jun 04, 2014 | Category B assigned | 
| Jun 06, 2014 | 30 day Public Notice Issued | 
| Jun 24, 2014 | Correspondence Received | 
| Jun 25, 2014 | Additional Information Received | 
| Jul 02, 2014 | Objections/Comments Received | 
| Jul 06, 2014 | Public Notice End Date | 
| Jul 09, 2014 | Plans Received | 
| Aug 04, 2014 | US Army Corps of Engineers Approval Received | 
| Oct 15, 2014 | Dock Meeting -- Approval | 
| Oct 20, 2014 | Additional Information Received | 
| Nov 12, 2014 | Plans Received | 
| Nov 17, 2014 | Plans Received | 
| Nov 21, 2014 | Engineering Report | 
| Nov 21, 2014 | Biologist Report | 
| Nov 24, 2014 | Typist for Processing | 
| Nov 24, 2014 | Permit Approved | 
| Nov 25, 2014 | Executive Sign Off | 
| Nov 25, 2014 | Sent to Photo Copy | 
| Dec 19, 2014 | Land Evidence Date | 
| Jan 05, 2015 | Commencement of Work Notice received |