| Action Date | Action Description | 
|---|---|
| Dec 04, 2014 | Freshwater Wetland - Request to Alter | 
| Dec 05, 2014 | Administrative Review for Completeness | 
| Dec 08, 2014 | Team Review for Completeness | 
| Dec 10, 2014 | Application Accepted | 
| Jan 20, 2015 | HPHC Historical Preservation Comments/Concerns | 
| Mar 11, 2015 | Additional Information Received | 
| Mar 16, 2015 | Additional Information Requested from Applicant | 
| May 05, 2015 | Plans Received | 
| May 19, 2015 | Biologist Report | 
| May 22, 2015 | Typist for Processing | 
| May 26, 2015 | Executive Sign Off | 
| May 26, 2015 | Sent to Photo Copy | 
| Jun 04, 2015 | Land Evidence Date | 
| Sep 13, 2018 | Modification Request | 
| Sep 13, 2018 | Administrative Review for Completeness | 
| Oct 22, 2018 | Team Review for Completeness | 
| Oct 22, 2018 | Additional Information Received | 
| Oct 22, 2018 | Application Accepted | 
| Oct 23, 2018 | Additional Information Received | 
| Nov 29, 2018 | HPHC Historical Preservation Comments/Concerns | 
| Dec 17, 2018 | Additional Information Received | 
| Jan 07, 2019 | HPHC Historical Preservation No Effect | 
| Jan 10, 2019 | Plans Received | 
| Feb 05, 2019 | Biologist Report | 
| Feb 07, 2019 | Typist for Processing | 
| Feb 07, 2019 | Executive Sign Off | 
| Feb 07, 2019 | Sent to Photo Copy | 
| Feb 07, 2019 | Modification Approved | 
| Mar 04, 2019 | Land Evidence Date |