| Action Date | Action Description | 
|---|---|
| May 16, 2017 | Assent Application Received | 
| May 17, 2017 | Administrative Review for Completeness | 
| May 22, 2017 | Team Review for Completeness | 
| May 22, 2017 | Deficient Application - Owner Notification Sent | 
| Aug 08, 2017 | Deficiency Response Received | 
| Aug 11, 2017 | Team Review for Completeness | 
| Aug 11, 2017 | Application Accepted | 
| Aug 23, 2017 | HPHC Historical Preservation No Effect | 
| Aug 24, 2017 | 30 day Public Notice Issued | 
| Sep 25, 2017 | Public Notice End Date | 
| Nov 30, 2017 | Dock Meeting -- Approval | 
| Dec 06, 2017 | Biologist Report | 
| Dec 07, 2017 | Plans Received | 
| Dec 20, 2017 | Category B assigned | 
| Dec 20, 2017 | Executive Sign Off | 
| Dec 20, 2017 | Sent to Photo Copy | 
| Dec 20, 2017 | Permit Approved | 
| Dec 20, 2017 | Typist for Processing | 
| Feb 23, 2018 | Land Evidence Date | 
| May 02, 2019 | Dock Post-Construction Certification by Engineer received. |