| Action Date | Action Description | 
|---|---|
| Oct 08, 2020 | Bio Team Review for Completeness | 
| Oct 08, 2020 | Application Accepted | 
| Oct 08, 2020 | Assent Application Received | 
| Oct 08, 2020 | Administrative Review for Completeness | 
| Oct 09, 2020 | Project Manager | 
| Oct 16, 2020 | Plans Received | 
| Oct 26, 2020 | HPHC Historical Preservation No Effect | 
| Oct 26, 2020 | HPHC Review Pending | 
| Nov 30, 2020 | Plans Received | 
| Dec 08, 2020 | Stipulation Package from Biologist | 
| Dec 08, 2020 | Typist for Processing | 
| Dec 08, 2020 | Executive Sign Off | 
| Dec 08, 2020 | Sent to Photo Copy | 
| Dec 08, 2020 | Permit Approved | 
| Dec 08, 2020 | Biologist Report | 
| Jun 15, 2021 | Duplicate Original Assent requested/mailed | 
| Jun 18, 2021 | Land Evidence Date |