| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Feb 04, 2021 | Assent Application Received | 
| Feb 05, 2021 | Administrative Review for Completeness | 
| Feb 09, 2021 | Category A* (Docks) | 
| Feb 10, 2021 | Application Accepted | 
| Feb 10, 2021 | Project Manager | 
| Feb 10, 2021 | Eng Team Review for Completeness | 
| Feb 17, 2021 | HPHC Review Pending | 
| Feb 17, 2021 | HPHC Historical Preservation No Effect | 
| Feb 19, 2021 | 30 day Public Notice Issued | 
| Feb 25, 2021 | Comments Received | 
| Mar 12, 2021 | Comments Received | 
| Mar 15, 2021 | US Army Corps of Engineers Approval Received | 
| Mar 19, 2021 | Public Notice End Date | 
| Mar 30, 2021 | US Army Corps of Engineers Approval Received | 
| May 04, 2021 | Stipulation Package by Engineer | 
| May 04, 2021 | Engineering Report | 
| May 06, 2021 | Typist for Processing | 
| May 06, 2021 | Executive Sign Off | 
| May 06, 2021 | Permit Approved | 
| May 06, 2021 | Sent to Photo Copy | 
| May 19, 2021 | Land Evidence Date |