| Action Date | Action Description | 
|---|---|
| Feb 16, 2022 | Assent Application Received | 
| Feb 18, 2022 | Administrative Review for Completeness | 
| Feb 18, 2022 | CHA Worksheet received | 
| Feb 23, 2022 | Bio Team Review for Completeness | 
| Feb 23, 2022 | Application Accepted | 
| Feb 24, 2022 | Project Manager | 
| Mar 21, 2022 | HPHC Review Pending | 
| Mar 21, 2022 | Additional Information Requested from Applicant | 
| Mar 21, 2022 | HPHC Historical Preservation No Effect | 
| Mar 24, 2022 | Phone Call | 
| Mar 24, 2022 | Phone Call | 
| Mar 25, 2022 | Additional Information Received | 
| Apr 06, 2022 | Additional Information Requested from Applicant | 
| Apr 12, 2022 | Additional Information Requested from Applicant | 
| Apr 13, 2022 | Additional Information Received | 
| Apr 14, 2022 | Additional Information Received | 
| Apr 14, 2022 | Correspondence Mailed/Faxed/E-mailed | 
| Apr 14, 2022 | Plans Received | 
| Apr 28, 2022 | Biologist Report | 
| May 02, 2022 | Typist for Processing | 
| May 02, 2022 | Executive Sign Off | 
| May 02, 2022 | Sent to Photo Copy | 
| May 02, 2022 | Permit Approved | 
| May 04, 2022 | Permit Mailed | 
| Jul 18, 2022 | Land Evidence Date |