| Action Date | Action Description | 
|---|---|
| Feb 22, 2022 | Assent Application Received | 
| Mar 01, 2022 | Administrative Review for Completeness | 
| Mar 21, 2022 | Eng Team Review for Completeness | 
| Mar 21, 2022 | Deficient Application - Owner Notification Sent | 
| May 04, 2022 | Deficiency Response Received | 
| May 12, 2022 | Eng Team Review for Completeness | 
| May 12, 2022 | Application Accepted | 
| May 19, 2022 | Project Manager | 
| Jun 02, 2022 | HPHC Review Pending | 
| Jun 02, 2022 | HPHC Historical Preservation No Effect | 
| Jun 29, 2022 | Engineering Report | 
| Jul 06, 2022 | Permit Mailed | 
| Jul 06, 2022 | Typist for Processing | 
| Jul 06, 2022 | Executive Sign Off | 
| Jul 06, 2022 | Sent to Photo Copy | 
| Jul 06, 2022 | Permit Approved | 
| Aug 08, 2022 | Land Evidence Date |