| Action Date | Action Description | 
|---|---|
| Jun 03, 2022 | Maintenance Certification Request | 
| Jun 08, 2022 | Administrative Review for Completeness | 
| Jun 10, 2022 | Eng Team Review for Completeness | 
| Jun 10, 2022 | Application Accepted | 
| Jun 13, 2022 | Project Manager | 
| Jul 07, 2022 | HPHC Review Pending | 
| Jul 07, 2022 | HPHC Historical Preservation No Effect | 
| Nov 04, 2022 | Correspondence Mailed/Faxed/E-mailed | 
| Jan 10, 2023 | Plans Received | 
| Feb 14, 2023 | Engineering Report | 
| Mar 08, 2023 | Typist for Processing | 
| Mar 08, 2023 | Executive Sign Off | 
| Mar 08, 2023 | Sent to Photo Copy | 
| Mar 08, 2023 | Permit Approved | 
| Mar 14, 2023 | Permit Mailed | 
| Mar 22, 2023 | Land Evidence Date | 
| Mar 29, 2023 | Commencement of Work Notice received |