| Action Date | Action Description | 
|---|---|
| Jun 14, 2022 | Assent Application Received | 
| Jun 20, 2022 | Administrative Review for Completeness | 
| Jun 21, 2022 | Bio Team Review for Completeness | 
| Jun 21, 2022 | Application Accepted | 
| Jun 22, 2022 | Project Manager | 
| Jul 08, 2022 | HPHC Historical Preservation No Effect | 
| Jul 08, 2022 | HPHC Review Pending | 
| Aug 17, 2022 | Permit Mailed | 
| Aug 17, 2022 | Typist for Processing | 
| Aug 17, 2022 | Executive Sign Off | 
| Aug 17, 2022 | Sent to Photo Copy | 
| Aug 17, 2022 | Permit Approved | 
| Aug 17, 2022 | Biologist Report | 
| Sep 02, 2022 | Land Evidence Date | 
| Aug 01, 2023 | Commencement of Work Notice received |