| Action Date | Action Description | 
|---|---|
| Enforcement Compliance Inspection Required | |
| Jun 20, 2022 | Freshwater Wetland - Preliminary Determination | 
| Jun 23, 2022 | Administrative Review for Completeness | 
| Jun 24, 2022 | Bio Team Review for Completeness | 
| Jun 24, 2022 | Application Accepted | 
| Jun 24, 2022 | Project Manager | 
| Jul 22, 2022 | HPHC Historical Preservation No Effect | 
| Jul 22, 2022 | HPHC Review Pending | 
| Sep 14, 2022 | Correspondence Mailed/Faxed/E-mailed | 
| Oct 31, 2022 | Additional Information Requested from Applicant | 
| Nov 28, 2022 | Additional Information Received | 
| Dec 14, 2022 | Biologist Report | 
| Dec 14, 2022 | Category A assigned | 
| Dec 28, 2022 | Typist for Processing | 
| Jan 03, 2023 | Executive Sign Off | 
| Jan 03, 2023 | Sent to Photo Copy | 
| Jan 03, 2023 | Permit Approved | 
| Jan 04, 2023 | Permit Mailed | 
| Jan 31, 2023 | Land Evidence Date | 
| Sep 29, 2025 | Extension of Permit Request |