| Action Date | Action Description | 
|---|---|
| Jul 22, 2022 | CHA Worksheet received | 
| Jul 22, 2022 | Assent Application Received | 
| Jul 29, 2022 | Administrative Review for Completeness | 
| Aug 10, 2022 | Bio Team Review for Completeness | 
| Aug 10, 2022 | Deficient Application - Owner Notification Sent | 
| Oct 25, 2022 | Deficiency Response Received | 
| Nov 10, 2022 | Bio Team Review for Completeness | 
| Nov 10, 2022 | Plans Received | 
| Nov 10, 2022 | Application Accepted | 
| Nov 10, 2022 | Project Manager | 
| Dec 20, 2022 | HPHC Historical Preservation No Effect | 
| Mar 14, 2023 | Additional Information Received | 
| Mar 14, 2023 | Correspondence Mailed/Faxed/E-mailed | 
| Apr 05, 2023 | Biologist Report | 
| Apr 21, 2023 | Typist for Processing | 
| Apr 21, 2023 | Executive Sign Off | 
| Apr 21, 2023 | Sent to Photo Copy | 
| Apr 21, 2023 | Permit Approved | 
| Apr 27, 2023 | Permit Mailed | 
| Oct 03, 2023 | Land Evidence Date |