| Action Date | Action Description | 
|---|---|
| Jul 03, 2023 | Assent Application Received | 
| Jul 07, 2023 | Administrative Review for Completeness | 
| Jul 07, 2023 | Bio Team Review for Completeness | 
| Jul 07, 2023 | Application Accepted | 
| Jul 07, 2023 | Project Manager | 
| Aug 30, 2023 | Plans Received | 
| Sep 08, 2023 | HPHC Historical Preservation No Effect | 
| Sep 13, 2023 | 30 day Public Notice Issued | 
| Sep 28, 2023 | Dock Meeting -- Approval | 
| Oct 10, 2023 | Objections/Comments Received | 
| Oct 12, 2023 | Objections/Comments Received | 
| Oct 13, 2023 | Public Notice End Date | 
| Apr 18, 2024 | Additional Information Received | 
| May 10, 2024 | Dock/1.1.6 Review approval | 
| May 13, 2024 | Biologist Report | 
| May 14, 2024 | Typist for Processing | 
| May 14, 2024 | Executive Sign Off | 
| May 14, 2024 | Sent to Photo Copy | 
| May 14, 2024 | Permit Approved | 
| May 17, 2024 | Permit Mailed | 
| Oct 01, 2024 | Land Evidence Date | 
| Nov 06, 2024 | Commencement of Work Notice received | 
| Jun 23, 2025 | Additional Information Received | 
| Jul 02, 2025 | Additional Information Received | 
| Oct 08, 2025 | Additional Information Received | 
| Oct 14, 2025 | Dock Post-Construction Certification by Engineer received. |