| Action Date | Action Description | 
|---|---|
| Land Evidence Date | |
| Dock Post-Construction Certification by Engineer received. | |
| Dec 06, 2023 | Assent Application Received | 
| Dec 07, 2023 | Administrative Review for Completeness | 
| Apr 08, 2024 | Bio Team Review for Completeness | 
| Apr 08, 2024 | Application Accepted | 
| Apr 08, 2024 | Project Manager | 
| Apr 08, 2024 | Category A* (Docks) | 
| Apr 08, 2024 | 30 day Public Notice Issued | 
| Apr 12, 2024 | HPHC Historical Preservation No Effect | 
| May 08, 2024 | Public Notice End Date | 
| Jul 10, 2024 | Dock/1.1.6 Review approval | 
| Sep 11, 2024 | Biologist Report | 
| Sep 12, 2024 | Typist for Processing | 
| Sep 12, 2024 | Executive Sign Off | 
| Sep 12, 2024 | Sent to Photo Copy | 
| Sep 12, 2024 | Permit Approved | 
| Sep 16, 2024 | Permit Mailed |