| Action Date | Action Description | 
|---|---|
| Land Evidence Date | |
| Jan 31, 2025 | Maintenance Certification Request | 
| Feb 07, 2025 | Administrative Review for Completeness | 
| Mar 04, 2025 | Eng Team Review for Completeness | 
| Mar 04, 2025 | Deficient Application - Owner Notification Sent | 
| Apr 24, 2025 | Deficiency Response Received | 
| May 07, 2025 | Eng Team Review for Completeness | 
| May 07, 2025 | Additional Information Received | 
| May 07, 2025 | Application Accepted | 
| May 07, 2025 | Project Manager | 
| May 22, 2025 | HPHC Historical Preservation No Effect | 
| May 28, 2025 | Permit Approved | 
| May 28, 2025 | Engineering Report | 
| May 30, 2025 | Permit Mailed | 
| Jun 02, 2025 | Commencement of Work Notice received |