| Action Date | Action Description |
|---|---|
| Feb 09, 2005 | Assent Application Received |
| Feb 10, 2005 | Administrative Review for Completeness |
| Feb 10, 2005 | Team Review for Completeness |
| Feb 10, 2005 | Application Accepted |
| Feb 14, 2005 | 30 day Public Notice Issued |
| Feb 15, 2005 | HPHC Review Pending |
| Mar 10, 2005 | Correspondence Received |
| Mar 16, 2005 | Public Notice End Date |
| Mar 18, 2005 | Typist for Processing |
| Mar 18, 2005 | Executive Sign Off |
| Mar 18, 2005 | Sent to Photo Copy |
| Mar 18, 2005 | Permit Approved |
| Mar 18, 2005 | Biologist Report |
| Mar 18, 2005 | Engineering Report |
| Mar 29, 2005 | Land Evidence Date |
| Jul 15, 2005 | Commencement of Work Notice received |