| Action Date | Action Description |
|---|---|
| Monitoring Report | |
| Jun 26, 2006 | Assent Application Received |
| Jun 27, 2006 | Administrative Review for Completeness |
| Jul 14, 2006 | Team Review for Completeness |
| Jul 14, 2006 | Application Accepted |
| Jul 14, 2006 | Category B assigned |
| Jul 27, 2006 | 30 day Public Notice Issued |
| Aug 24, 2006 | Meeting Held |
| Aug 27, 2006 | Public Notice End Date |
| Nov 20, 2006 | Plans Received |
| Dec 20, 2006 | HPHC Historical Preservation Comments/Concerns |
| Dec 21, 2006 | HPHC Historical Preservation Comments/Concerns |
| Mar 09, 2007 | Additional Information Received |
| Apr 09, 2007 | Engineering Report |
| Apr 16, 2007 | US Army Corp of Engineers Permit Date |
| Apr 18, 2007 | US Army Corps of Engineers Approval Received |
| Jul 02, 2007 | Correspondence Received |
| Jul 23, 2007 | Plans Received |
| Jul 27, 2007 | Public Hearing Notices Mailed |
| Jul 30, 2007 | Water Quality Certification |
| Aug 03, 2007 | Biologist Report |
| Aug 28, 2007 | Special Exception Scheduled for Semi-Monthly |
| Aug 28, 2007 | Semi-Monthly Meeting Held |
| Aug 28, 2007 | Council Approval Granted |
| Sep 05, 2007 | Legal Response/Decision |
| Sep 11, 2007 | Stipulation Package from Biologist |
| Sep 12, 2007 | Stipulation Package by Engineer |
| Sep 12, 2007 | Permit Approved |
| Sep 12, 2007 | Typist for Processing |
| Sep 12, 2007 | Executive Sign Off |
| Sep 12, 2007 | Sent to Photo Copy |
| Sep 21, 2007 | Land Evidence Date |
| Oct 17, 2007 | Correspondence Received |
| Dec 17, 2007 | Monitoring Report |
| Jan 04, 2008 | Monitoring Report |
| Mar 11, 2008 | Monitoring Report |
| Apr 29, 2008 | Monitoring Report |
| May 22, 2008 | Modification Request |
| May 23, 2008 | Administrative Review for Completeness |
| May 29, 2008 | Team Review for Completeness |
| May 29, 2008 | Engineering Report |
| May 29, 2008 | Typist for Processing |
| May 29, 2008 | Executive Sign Off |
| May 29, 2008 | Sent to Photo Copy |
| May 29, 2008 | Modification Approved |
| Jun 05, 2008 | Land Evidence Date |
| Jun 06, 2008 | Monitoring Report |
| Aug 18, 2008 | Monitoring Report |
| Aug 19, 2009 | Monitoring Report |
| Mar 10, 2010 | Monitoring Report |
| May 13, 2010 | Monitoring Report |
| May 24, 2010 | Letter of Authorization |
| Aug 11, 2010 | Monitoring Report |
| Aug 13, 2010 | Additional Information Received |
| Nov 18, 2010 | Monitoring Report |