| Action Date | Action Description |
|---|---|
| Nov 29, 2011 | Assent Application Received |
| Nov 30, 2011 | Administrative Review for Completeness |
| Dec 06, 2011 | Team Review for Completeness |
| Dec 07, 2011 | Team Review for Completeness |
| Dec 07, 2011 | Application Accepted |
| Jan 14, 2012 | HPHC Historical Preservation No Effect |
| Apr 29, 2013 | Correspondence Received |
| Sep 19, 2013 | Plans Received |
| Sep 23, 2013 | Biologist Report |
| Sep 23, 2013 | Engineering Report |
| Sep 24, 2013 | Permit Approved |
| Sep 25, 2013 | Typist for Processing |
| Sep 25, 2013 | Executive Sign Off |
| Sep 25, 2013 | Sent to Photo Copy |
| Oct 11, 2013 | Land Evidence Date |