| Action Date | Action Description |
|---|---|
| Feb 14, 2012 | Assent Application Received |
| Feb 14, 2012 | Administrative Review for Completeness |
| Feb 16, 2012 | Team Review for Completeness |
| Feb 16, 2012 | Application Accepted |
| Feb 27, 2012 | Correspondence Mailed/Faxed/E-mailed |
| Mar 12, 2012 | Additional Information Received |
| Apr 03, 2012 | HPHC Historical Preservation No Effect |
| Apr 03, 2012 | Biologist Report |
| Apr 05, 2012 | Typist for Processing |
| Apr 05, 2012 | Permit Approved |
| Apr 09, 2012 | Executive Sign Off |
| Apr 09, 2012 | Sent to Photo Copy |
| Apr 25, 2012 | Land Evidence Date |