| Action Date | Action Description |
|---|---|
| Jan 19, 2016 | Assent Application Received |
| Jan 19, 2016 | Administrative Review for Completeness |
| Jan 26, 2016 | Team Review for Completeness |
| Jan 26, 2016 | Deficiency - Phone Call to Applicant/Owner |
| Feb 02, 2016 | Deficient Application Picked Up |
| Feb 25, 2016 | Deficiency Response Received |
| Feb 29, 2016 | Deficiency Response Received |
| Mar 01, 2016 | Team Review for Completeness |
| Mar 01, 2016 | Application Accepted |
| Mar 08, 2016 | Biologist Report |
| Mar 11, 2016 | Typist for Processing |
| Mar 11, 2016 | Executive Sign Off |
| Mar 11, 2016 | Sent to Photo Copy |
| Mar 11, 2016 | Permit Approved |
| Mar 24, 2016 | Land Evidence Date |
| Apr 07, 2016 | HPHC Historical Preservation No Effect |