| Action Date | Action Description |
|---|---|
| Oct 17, 2018 | Assent Application Received |
| Oct 17, 2018 | Administrative Review for Completeness |
| Oct 19, 2018 | Team Review for Completeness |
| Oct 19, 2018 | Application Accepted |
| Nov 16, 2018 | Engineering Report |
| Nov 20, 2018 | Typist for Processing |
| Nov 20, 2018 | Executive Sign Off |
| Nov 20, 2018 | Sent to Photo Copy |
| Nov 20, 2018 | Permit Approved |
| Nov 27, 2018 | HPHC Historical Preservation No Effect |