| Action Date | Action Description |
|---|---|
| May 30, 2019 | Assent Application Received |
| May 30, 2019 | Administrative Review for Completeness |
| Jun 04, 2019 | Team Review for Completeness |
| Jun 04, 2019 | Application Accepted |
| Jul 03, 2019 | HPHC Review Pending |
| Jul 03, 2019 | HPHC Historical Preservation No Effect |
| Jul 10, 2019 | Additional Information Requested from Applicant |
| Jul 23, 2019 | Phone Call |
| Jul 26, 2019 | Plans Received |
| Aug 07, 2019 | Phone Call |
| Aug 13, 2019 | Additional Information Received |
| Aug 15, 2019 | Biologist Report |
| Aug 20, 2019 | Typist for Processing |
| Aug 20, 2019 | Executive Sign Off |
| Aug 20, 2019 | Sent to Photo Copy |
| Aug 20, 2019 | Permit Approved |
| Aug 27, 2019 | Land Evidence Date |