| Action Date | Action Description |
|---|---|
| Aug 14, 2019 | Assent Application Received |
| Aug 14, 2019 | Administrative Review for Completeness |
| Aug 20, 2019 | Team Review for Completeness |
| Aug 20, 2019 | Application Accepted |
| Sep 27, 2019 | HPHC Review Pending |
| Sep 27, 2019 | HPHC Historical Preservation No Effect |
| Sep 30, 2019 | Additional Information Received |
| Oct 16, 2019 | Biologist Report |
| Oct 23, 2019 | Typist for Processing |
| Oct 23, 2019 | Executive Sign Off |
| Oct 23, 2019 | Sent to Photo Copy |
| Oct 23, 2019 | Permit Approved |
| Dec 12, 2019 | Note to File |
| Jan 16, 2020 | Land Evidence Date |
| Jul 01, 2021 | Assent Requirement |
| Jul 13, 2021 | Modification Request |
| Jul 16, 2021 | Administrative Review for Completeness |
| Jul 28, 2021 | Bio Team Review for Completeness |
| Jul 29, 2021 | Project Manager |
| Aug 04, 2021 | HPHC Review Pending |
| Aug 05, 2021 | Biologist Report |
| Aug 05, 2021 | Stipulation Package from Biologist |
| Aug 05, 2021 | HPHC Historical Preservation No Effect |
| Aug 06, 2021 | Modification Approved |
| Aug 06, 2021 | Executive Sign Off |
| Aug 06, 2021 | Sent to Photo Copy |
| Aug 06, 2021 | Typist for Processing |
| Jan 13, 2022 | Land Evidence Date |