| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Feb 25, 2022 | Assent Application Received |
| Mar 03, 2022 | Administrative Review for Completeness |
| Apr 04, 2022 | Eng Team Review for Completeness |
| Apr 04, 2022 | Application Accepted |
| Apr 04, 2022 | Project Manager |
| Apr 04, 2022 | Category A* (Docks) |
| May 06, 2022 | HPHC Historical Preservation No Effect |
| Jun 01, 2022 | Plans Received |
| Jun 10, 2022 | Plans Received |
| Aug 15, 2022 | 30 day Public Notice Issued |
| Aug 29, 2022 | Plans Received |
| Sep 15, 2022 | Public Notice End Date |
| Sep 29, 2022 | Engineering Report |
| Oct 03, 2022 | Typist for Processing |
| Oct 03, 2022 | Executive Sign Off |
| Oct 03, 2022 | Sent to Photo Copy |
| Oct 03, 2022 | Permit Approved |
| Oct 03, 2022 | Permit Mailed |
| Oct 11, 2022 | Permit Mailed |
| Jan 11, 2023 | Land Evidence Date |