| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Mar 22, 2022 | Assent Application Received |
| Mar 23, 2022 | Administrative Review for Completeness |
| Apr 07, 2022 | Note to File |
| Apr 12, 2022 | Category A* (Docks) |
| Apr 14, 2022 | Note to File |
| Apr 14, 2022 | Application Accepted |
| Apr 14, 2022 | Project Manager |
| Apr 14, 2022 | Bio Team Review for Completeness |
| Apr 28, 2022 | HPHC Historical Preservation No Effect |
| Jun 21, 2022 | Correspondence Mailed/Faxed/E-mailed |
| Jun 27, 2022 | Correspondence Received |
| Jun 28, 2022 | Correspondence Received |
| Jul 25, 2022 | Correspondence Mailed/Faxed/E-mailed |
| Jul 26, 2022 | Plans Received |
| Jul 28, 2022 | Additional Information Received |
| Jul 28, 2022 | Additional Information Requested from Applicant |
| Jul 28, 2022 | Additional Information Received |
| Jul 29, 2022 | Plans Received |
| Aug 25, 2022 | 30 day Public Notice Issued |
| Sep 25, 2022 | Public Notice End Date |
| Oct 03, 2022 | Biologist Report |
| Oct 07, 2022 | Permit Mailed |
| Oct 07, 2022 | Typist for Processing |
| Oct 07, 2022 | Executive Sign Off |
| Oct 07, 2022 | Sent to Photo Copy |
| Oct 07, 2022 | Permit Approved |
| Oct 13, 2022 | Permit Mailed |
| Jan 27, 2023 | Land Evidence Date |