| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Aug 19, 2022 | Assent Application Received |
| Aug 22, 2022 | Administrative Review for Completeness |
| Aug 23, 2022 | Eng Team Review for Completeness |
| Aug 23, 2022 | Application Accepted |
| Aug 24, 2022 | Project Manager |
| Aug 24, 2022 | Category A* (Docks) |
| Sep 21, 2022 | HPHC Historical Preservation No Effect |
| Oct 05, 2022 | US Army Corps of Engineers Approval Received |
| Oct 22, 2022 | Public Notice End Date |
| Jan 11, 2023 | Typist for Processing |
| Jan 11, 2023 | Executive Sign Off |
| Jan 11, 2023 | Sent to Photo Copy |
| Jan 11, 2023 | Permit Approved |
| Jan 11, 2023 | Engineering Report |
| Jan 13, 2023 | Permit Mailed |
| Jan 27, 2023 | Land Evidence Date |
| Dec 04, 2023 | Modification Request |
| Dec 05, 2023 | Administrative Review for Completeness |
| Dec 13, 2023 | Eng Team Review for Completeness |
| Dec 13, 2023 | Project Manager |
| Dec 13, 2023 | Application Accepted |
| Jan 17, 2024 | HPHC Historical Preservation No Effect |
| May 20, 2024 | Additional Information Received |
| Aug 22, 2024 | Additional Information Received |
| Sep 05, 2024 | 30 day Public Notice Issued |
| Sep 16, 2024 | Objections/Comments Received |
| Oct 05, 2024 | Public Notice End Date |
| Oct 29, 2024 | Correspondence Received |
| Nov 14, 2024 | Supervisor Engineer SignOff |
| Nov 14, 2024 | Executive Signoff of Staff Reports |
| Nov 14, 2024 | Mail Agenda Notice |
| Nov 14, 2024 | Engineering Report |
| Nov 26, 2024 | Council Approval Granted |
| Nov 26, 2024 | Semi-Monthly Meeting Date Scheduled |
| Aug 26, 2025 | Legal Response/Decision |
| Aug 26, 2025 | 30 Day Appeal Notification to Owner |
| Sep 02, 2025 | Stipulation Package by Engineer |
| Sep 09, 2025 | Modification Approved |
| Sep 09, 2025 | Modification mailed |
| Sep 09, 2025 | Dock Post-Construction Certification by Engineer Required. |
| Nov 03, 2025 | Land Evidence Date |