| Action Date | Action Description |
|---|---|
| Aug 22, 2005 | Assent Application Received |
| Aug 23, 2005 | Administrative Review for Completeness |
| Aug 24, 2005 | Team Review for Completeness |
| Aug 24, 2005 | Application Accepted |
| Aug 24, 2005 | Category A* (Docks) |
| Aug 30, 2005 | 30 day Public Notice Issued |
| Sep 01, 2005 | Engineering Report |
| Sep 06, 2005 | HPHC Review Pending |
| Sep 15, 2005 | Dock Subcommittee Meeting Held |
| Sep 15, 2005 | Dock sub-committee Approved |
| Sep 26, 2005 | US Army Corp of Engineers Permit Date |
| Sep 29, 2005 | US Army Corps of Engineers Approval Received |
| Sep 30, 2005 | Public Notice End Date |
| Oct 04, 2005 | Biologist Report |
| Oct 04, 2005 | Engineering Report |
| Oct 05, 2005 | Typist for Processing |
| Oct 05, 2005 | Executive Sign Off |
| Oct 05, 2005 | Sent to Photo Copy |
| Oct 05, 2005 | Permit Approved |
| Nov 29, 2005 | Land Evidence Date |