| Action Date | Action Description |
|---|---|
| Sep 23, 2005 | Assent Application Received |
| Sep 23, 2005 | Administrative Review for Completeness |
| Sep 26, 2005 | Team Review for Completeness |
| Sep 26, 2005 | Application Accepted |
| Sep 26, 2005 | Category A* (Docks) |
| Oct 05, 2005 | Historical Preservation Approval Granted |
| Oct 05, 2005 | HPHC Review Pending |
| Dec 01, 2005 | Plans Received |
| Dec 09, 2005 | 30 day Public Notice Issued |
| Jan 09, 2006 | Public Notice End Date |
| Jan 18, 2006 | US Army Corp of Engineers Permit Date |
| Jan 20, 2006 | US Army Corps of Engineers Approval Received |
| Jan 24, 2006 | Biologist Report |
| Jan 24, 2006 | Engineering Report |
| Jan 30, 2006 | Plans Received |
| Feb 16, 2006 | Supervisor Biologist SignOff |
| Feb 16, 2006 | Supervisor Engineer SignOff |
| Feb 17, 2006 | Executive Sign Off |
| Mar 30, 2006 | Ready to Schedule Semi-Monthly Meeting |
| Mar 30, 2006 | Mail Agenda Notice |
| Apr 11, 2006 | Semi-Monthly Meeting Held |
| Apr 11, 2006 | Council Approval Granted |
| Apr 11, 2006 | Semi-Monthly Meeting Date Scheduled |
| Apr 19, 2006 | Stipulation Package from Biologist |
| Apr 19, 2006 | Stipulation Package by Engineer |
| Apr 19, 2006 | Typist for Processing |
| Apr 19, 2006 | Executive Sign Off |
| Apr 19, 2006 | Sent to Photo Copy |
| Apr 19, 2006 | Permit Approved |
| Apr 24, 2006 | Legal Response/Decision |
| Apr 26, 2006 | Under Review/Decision |
| Jul 03, 2006 | Land Evidence Date |