| Action Date | Action Description |
|---|---|
| Nov 25, 2005 | Assent Application Received |
| Nov 28, 2005 | Administrative Review for Completeness |
| Dec 02, 2005 | Team Review for Completeness |
| Dec 02, 2005 | Application Accepted |
| Dec 02, 2005 | Category A* (Docks) |
| Dec 13, 2005 | HPHC Historical Preservation No Effect |
| Dec 14, 2005 | 30 day Public Notice Issued |
| Feb 16, 2006 | Correspondence Received |
| Feb 17, 2006 | US Army Corp of Engineers Permit Date |
| Feb 17, 2006 | US Army Corps of Engineers Approval Received |
| Feb 20, 2006 | Public Notice End Date |
| Mar 28, 2006 | Biologist Report |
| Mar 28, 2006 | Engineering Report |
| Mar 31, 2006 | Dock Meeting Scheduled (Admin) |
| Mar 31, 2006 | Dock sub-committee Approved |
| Apr 03, 2006 | Typist for Processing |
| Apr 03, 2006 | Executive Sign Off |
| Apr 03, 2006 | Sent to Photo Copy |
| Apr 03, 2006 | Permit Approved |
| Apr 10, 2006 | Land Evidence Date |