| Action Date | Action Description |
|---|---|
| Sep 17, 2013 | Assent Application Received |
| Sep 18, 2013 | Administrative Review for Completeness |
| Sep 27, 2013 | Team Review for Completeness |
| Sep 27, 2013 | Application Accepted |
| Oct 07, 2013 | 30 day Public Notice Issued |
| Oct 17, 2013 | Additional Information Received |
| Oct 18, 2013 | Additional Information Received |
| Nov 01, 2013 | Public Notice End Date Extension Granted |
| Nov 05, 2013 | HPHC Historical Preservation No Effect |
| Nov 07, 2013 | Public Notice End Date |
| Nov 12, 2013 | Correspondence Received |
| Mar 21, 2014 | Plans Received |
| Apr 10, 2014 | Plans Received |
| Apr 23, 2014 | Plans Received |
| Apr 25, 2014 | Biologist Report |
| Apr 25, 2014 | Engineering Report |
| May 08, 2014 | Permit Approved |
| May 13, 2014 | Typist for Processing |
| May 13, 2014 | Executive Sign Off |
| May 13, 2014 | Sent to Photo Copy |
| Sep 03, 2014 | Land Evidence Date |